Clackamas County logo

Capital Improvement Program

Five (5) Year Transportation Capital Improvement Program and Twenty (20) Year Transportation Capital Improvement Plan

Clackamas County is responsible for over 1,436 miles of roads and 158 bridges in its 1,868 square mile territory. The county's transportation system represents a one billion dollar investment that must continually be maintained and improved to handle new demands. The "Capital Improvement Plan and Program" for the County documents the 20-Year Plan for capital transportation projects needed in the next twenty years, and the 5-Year Program of high-priority, funded projects that are slated for construction in the near term.

The transportation network in the county serves a population that has increased to an estimated 361,000 persons (July 2005), an rise of approximately 6.3% since 2000. This growing population brought an increase of 8.4% in the number of vehicles (not including trailers) registered in the County and an increase of 5.8% in the number of driver’s licenses issued. (These increases were for the five years ending in December 2005.)

As fiscal year 2006/2007 began, the County had fifteen active capital projects underway, with an estimated value of $68 million. The upcoming 5-Year Program for 2006/07 through 2010/11 has another twenty-five projects set to begin construction; these projects have an estimated value of over $84 million. In addition to the active and programmed projects, the 5-Year Program now includes the set of high-priority, "Project Development" projects. These projects will be funded for planning and preliminary design work, with the goal to make them highly eligible for future construction funding from state and federal revenue sources. (The 5-Year Program table is included here.)

The 20-Year Plan has 224 transportation improvement projects that are projected to be needed over the next twenty years. However, the current cost estimate (2006 dollars) shows a minimum need of $787.7 million, while the forecasted revenues of $358.7 leave a $429 million funding shortfall.

Clackamas County 5-Year Program

Projects set to begin construction, 2006/07 – 2010/11
and
Projects in “Project Development,” 2006/07 – 2007/08

Map location numbers can be found on the urban projects map and the rural projects map.

Map #PROJECTSECTIONDESCRIPTIONProgram Year
3Johnson Creek (Johnson Creek Blvd.) Bridge Bridge 6891DReconstruct / widen 5 lanes, 74 ft. pavement curb to curb (24x64)2006/07
1577th - 79th west collector road Johnson Creek Blvd. south to King RoadAnalyze new collector road west of 82nd Avenue to provide capacity for north-south traffic movement.Project Development 2006/07 - 2007/08
18Fuller Road (Project related to LRT and Otty Rd. project, Map #20) Johnson Creek Boulevard to Otty RoadEngineer widening of Fuller Road to three lanes.Project Development 2006/07 - 2007/08
20Otty Road (Project related to LRT and Fuller Road project, Map #18)82nd Ave. to I-205Evaluate improvement to minor arterial standard, with bike lanes, sidewalks and double left-turn lanes for westbound traffic.Project Development 2006/07 - 2007/08
31Monterey Avenue82nd to 92ndWiden to 3 lanes, parking, main street standards. Should be in design with the Town Center design.2006/07
35Harmony Road (also CIP Map #34, railroad overcrossing at Linwood/Harmony)82nd Ave. to Hwy. 224Evaluate widening to 5 lanes and railroad overpass. Project Development 2006/07 - 2007/08
36Sunnybrook Road extension west of 82nd82nd Ave. to Harmony Rd.Extend new minor arterial street.2006/07
55Causey Avenue extension east of I-205 Schumacher Rd. east to Stevens Rd.Complete to collector standards; add left turn bays on Schumacher Rd.2005/06
60Sunnyside Road, Phase 2.1 122nd Ave. to 152nd Ave.Widen to 5 lanes to 152nd; complete final design to 172nd2005/06
62Sunnyside Rd, Phase 3 152nd to 172nd (Construct Ph 3A, 152nd-162nd, w/ Ph 2.1)Widen to 5 lanes2005/06
63172nd Ave/Sunnyside Road 172nd / Sunnyside intersectionAdd left turn lanes and traffic signal2005/06
65172nd at Armstrong Circle Armstrong Circle to Hwy 212Extend 172nd to Hwy 212 2006/07
71122nd Avenue Sunnyside Road to Hubbard RoadAdd left turn lanes, sidewalk, bike lanes on 122nd, Hwy 212 to Sunnyside.2008/09
101Industrial Way [Coordinate project scope with Sunrise Corridor plan] Lawnfield to Mather Rd.New road to connect Lawnfield to Mather. Design after Sunrise Corridor's "Record of Decision" is signed.2008/09
105102nd Industrial Access improvements [Coordinate scope w/ Sunrise Corridor plan.]102nd to Mather Rd.Widen, add sidewalks, bike lanes and turn lanes. Design after Industrial Way project.2008/09
119Tualatin River (Stafford Rd.) BridgeBridge 2567Reconstruct and widen -- 50 ft. (24x450)2006/07
120Stafford Road Stafford / Borland intersectionAdd turn lanes and signal or roundabout2006/07
127Stafford RoadStafford / Mountain intersectionAdd turn lanes and realign intersection2006/07
135Clackamas River (Springwater Rd.) BridgeBridge 1446: Carver Truss - Baker BridgeReconstruct and widen to 74' (23 X 422)2006/07
160Beavercreek RoadHwy 213 to Henrici RoadEvaluate widening Beavercreek Road to five lanes.Project Development 2006/07 - 2007/08
179Evelyn / Jennifer St. Evelyn / Jennifer intersectionAdd signal2006/07
180172nd AvenueHwy 212 north to Sunnyside RoadComplete environmental work; R/W and construction assume 5-lane section.2007/08
181172nd Avenue, Phase 2 Sunnyside Road to Multnomah County lineProject Development to upgrade 172nd to five lanes.Project Development 2006/07 - 2007/08
18297th / Lawnfield 97th / Lawnfield intersectionAdd signal2007/08
183Sunrise Corridor, Unit 1I-205 to Rock Creek JunctionFinal supplemental EIS. Environmental analysis phase to be completed in fall 2006 with final EIS.Project Development 2006/07 - 2007/08
186Tualatin River (Borland Road) Bridge Bridge 6507Replace existing bridge2006/07
190Kellogg DriveKellogg Drive / Rusk Road intersectionImprove sight distance at intersection and improve ped/bike access.2005/06
204242nd at Borges Borges to Rugg RoadSafety project to realign curves2005/06
209282nd Avenue282nd / Stone intersectionRealign and widen, add turn lanes (partner with Multnomah County)2005/06
221Sandy River (Ten Eyck Rd.) BridgeBridge 6570Reconstruct / widen -- 32 ft. (22 x 200) 2006/07
225Salmon River (Arrah Wanna Rd) Bridge Bridge 6572Replace existing one-lane bridge with a two-lane bridge2006/07
257Wilsonville Road Wilsonville Rd/ Ladd Hill Rd. intersectionSafety project to remove bank; remove or decrease horizontal curve along Wilsonville Rd. / relocate intersection.2007/08
258Wilsonville Road Wilsonville Rd/ Edminston Rd. intersectionSafety project to remove bank; remove or decrease horizontal curve along Wilsonville Rd. / relocate intersection.2007/08
272Hwy 99EHwy 99E / Territorial Rd. intersectionSignalize intersection; improve RR crossing. ODOT is lead agency and funding the project. County costs are for staff time only.2005/06
304Milk Creek (Dhooghe Rd.) BridgeBridge 6541Reconstruct and widen. 2005/06
313Zigzag River (Lolo Pass Road) Bridge Bridge 6401 Replace existing bridge with simple-span steel bridge (2 travel lanes and shoulders)2005/06
318Milk Creek (Mulino Rd.) BridgeBridge 6511Replace existing bridge w/ structure: 2 travel lanes, sidewalks and bike lanes.2005/06
319Molalla River (Feyrer Park Rd.) BridgeBridge 605Replace existing bridge w/ structure w/ travel lanes; widen shoulders. 2005/06
320Buckner Creek (Beavercreek Road) BridgeBeavercreek Rd.Replace culvert with bridge2006/07
321Rock Creek (Kropf Rd) Bridge Bridge 6506Structural and functional deficiencies necessitate moving the stream back to its historic channel.2006/07
322Multorpor OverpassBridge project in Government CampReplace existing structure to accommodate 2 lanes of traffic, bike lanes and grade-separated pedestrian walkway.2005/06
323North Fork Molalla (Dickey Prairie Rd) BridgeBridge 6554Replace existing bridge. 2006/07
702Park Avenue River Road to Hwy 99ERoad/drainage improvements w/ sidewalk on one side of street.2006/07
70392nd Avenue Bike Lanes Johnson Creek Blvd. to County lineComplete missing bike lane links2005/06
704132nd AvenueSunnyside Road to middle schoolDesign and engineer sidewalk improvements2009/10
70513th Avenue bike lanes in Canby Teakwood to Molalla Forest RoadWiden for bike lanes2006/07
707Holcomb Blvd. Pedestrian Enhancement ProgramHwy 213 to Urban Growth BoundaryProposed Phase 1: Design pedestrian improvement to fill in gaps in sidewalks. City of Oregon City and Clackamas County 50/50 partnership.Project Development 2006/07 - 2007/08
708Pilkington Road Pedestrian Pathway ProjectChilds Road to Jean RoadEvaluate pedestrian path. City of Lake Oswego and Clackamas County partnership.Project Development 2006/07 - 2007/08
709Salmon River Rd. bike laneHwy 26 to Welches RoadEvaluate widening to provide bikeway on shoulderProject Development 2006/07 - 2007/08
710Welches Road bike laneHwy 26 to Salmon River RoadEvaluate widening to provide bikeway on shoulderProject Development 2006/07 - 2007/08
810Clackamas County ITS ProjectsCountywidePlan and implement arterial signal control improvements to enhance traffic flow and efficiency of the County transportation system.2005/06 - 2010/11
820Safety ProjectsTo be determinedSafety improvements at various locations.2008/09 - 2010/11

Ron Weinman: (503) 353-4533